Measure SP Construction Update South Pasadena Unified School District

Published : Tuesday, July 31, 2018 | 1:23 PM

South Pasadena High School STEM Building

Work during the summer months is continuing at a rapid pace. In August, the crew will apply exterior plaster to the northern section of the building and will install window glazing (glass). The interior drywall installation is underway.

Workers framed the southern section of the building and expect to complete the roof in August. In addition, electrical, plumbing and mechanical utilities inside the building are being installed.

South Pasadena High School Physical Education and Athletic Facility

The team is planning for a more fluid transition between the existing gymnasium, athletic field, baseball field, tennis courts and outdoor basketball courts. Final plans are expected to be completed and submitted to the Division of State Architect in October 2018.

South Pasadena Middle School Hard Court & Field Project

The athletic facilities and fields at South Pasadena Middle School are finished. Students and the community may now enjoy two new fields – one artificial and one natural grass along with revamped basketball and tennis courts. The project was completed on time and on budget.