Pasadena Central Library Renovation Awards Nearly $15 Million in Local Business Contracts

Nearly $15 million in construction contracts and related services has been awarded to businesses classified as local participants in Pasadena’s Central Library seismic retrofit and renovation project, according to newly released city documents detailing the economic impact of the continuing construction work.
The contracts, totaling $14,951,825 as of Sept. 30, involve mechanical systems, heating and air conditioning, fire protection, professional services and other work associated with restoring the historic library.
A Department of Public Works report dated Nov. 18 provides details of the awards, payments to participating companies and employment opportunities created by the project.
The report was prepared for the Municipal Services Committee’s Nov. 18 meeting, which the city canceled because of a lack of quorum.
ACCO Engineered Systems accounts for most of the awarded contract value, including $12.49 million for mechanical and heating, ventilation and air conditioning work during the second phase of construction.
The company also received a $1.73 million contract for fire sprinkler work and a $220,625 contract for earlier mechanical work, according to the city.
Other participating businesses include Pasadena-based Phillips Draperies and Curtains, which received a $219,200 subcontract.
Additional awards include $238,000 for professional services involving CSG, $46,800 for trailer cleaning services by Kleen and $7,200 for water services provided by Water Boy Services.
The report also identifies approximately $1.2 million in heating, ventilation and air conditioning controls work by Sunbelt Controls. That work is included in ACCO’s existing contract awards and is not counted a second time in the $14.95 million total.
Although nearly $15 million has been committed through the identified contracts, most of the money has not yet been paid.
As of Sept. 30, the city reported approximately $693,376 in cumulative payments, including $430,856 paid during the July-through-September quarter, leaving about $14.26 million in contract value to be paid as work progresses.
The figures distinguish contracts already awarded from actual expenditures, an important measure of how construction activity is translating into spending within the local economy.
The report also documents increasing participation by Pasadena construction workers.
During the July-through-September quarter, 28 Pasadena residents performed approximately 4,110 hours of construction craftwork, representing 8.74% of the total craft hours recorded during that period.
Those workers received approximately $317,577 in wages and employer-paid benefits, according to the city’s workforce utilization records.